After the competition had concluded, a series of planning steps and coordination measures were required before construction of the building could begin.
On the one hand, the planning team led by the architects worked with the future users to further develop the building. They determined the floor plan – in other words, the location of the exhibition spaces, storage areas, educational rooms, and gastronomy. They also refined the materiality of the façade, i.e. the outward appearance of the museum.
On the other hand, the building administration created the necessary technical prerequisites. For example, it examined the building site and arranged for the relocation of utility lines beneath the construction area.
Laying of the Foundation Stone and Current Status
Groundbreaking took place in December 2019, and on 9 February 2024 the foundation stone was laid – a major milestone for the project. Construction is now underway, implementing the further developed plans. The aim is a building that is socially and ecologically sustainable as well as inclusive.